Lubecka.Law Blog

Force majeure in international contracts

1. The meaning of force majeure in international agreements

In the past few years, there has been an increasing trend of including “force majeure” clauses in international contracts. The main objective of such clauses is to safeguard the parties’ interests in situations where fulfilling contractual obligations becomes impossible or significantly challenging due to unforeseeable and exceptional circumstances.

These clauses have also appeared in contracts before, but it was the coronavirus pandemic and the war in Ukraine that recently made it necessary to use legal mechanisms that had not had such a strong practical meaning so far. During that time, business owners were able to witness the significant effect that unforeseen and exceptional circumstances can have on the ability to fulfill contracts without interruption.

As it is for the pandemic the world is slowly returning to normality, and there is much less talking about coronavirus cases, many entrepreneurs still feel the severe effects caused by the pandemic, including: disruptions in supply chains, lack of availability of materials or lack of components.

Meanwhile, the world’s attention is drawn to the war in Ukraine, which calls into question the functioning of many branches of the economy. It should be remembered that even such basic obligations arising from contracts, as paying the contractor the remuneration may turn out to be impossible to perform or significantly hindered when international payment systems are blocked. The provisions of international and domestic legal acts concerning the introduction of certain types of sanctions, which prevent the performance of some of the existing contractual obligations, are also important.

All these circumstances mean that it is worth considering the regulation of cases of force majeure in the contract and the procedure of the parties in this type of situation. It is particular important in case of agreements under which there is an international supply of goods or provision of services in the territory of another country. Any disruption in the performance of such contracts may result in serious sanctions, e.g. in the form of contractual penalties, withdrawal from the contract or its termination.

2. Force Majeure - what is it?

The concept of force majeure has not been defined in the provisions of applicable law, however, the practice of trading allows to define circumstances that may be considered as cases of force majeure in contracts.

Events characterized by three features are considered force majeure:

  • externality,
  • unpredictability
  • and the impossibility of preventing its effects.

The manifestations of force majeure include: catastrophic phenomena caused by the forces of nature, e.g. floods, hurricanes, earthquakes, forest fires. Acts of public authority and social or political phenomena of catastrophic scale are also treated as force majeure[1].

Entrepreneurs have the option to specify in the contract what they consider to be a case of force majeure.

 

3. Contractual provisions regarding force majeure - what should they cover

3.1. Circumstances considered as force majeure

An agreement in the international trade should regulate the concept of force majeure and clearly indicate the cases connected with it. The absence of specific rules and regulations regarding the stated area can create substantial uncertainty and ambiguity during the execution of the contract. Typically, if one party has not been impacted by a force majeure event, they will aim to proceed with the agreement and dispute the opposing party’s claim of an obstacle to contract fulfillment. Conversely, if a force majeure event has affected one party, they will often seek to be absolved of their contractual duties.

 

3.2. How the parties should proceed in case of force majeure

The responsibility for deciding how force majeure affects contract performance is left to parties. This means they must address the following matters:

  • is the contract still in force, is its performance suspended for the period of force majeure, or do the parties terminate their contractual relation under the agreement?
  • are the parties obliged to perform further performances, and if so, to what extent?
  • will failure to perform all or a part of the contract due to force majeure result in the release of the party affected by force majeure from contractual liability towards the contractor?

 

3.3. Information obligation of the parties

While introducing regulations connected with the concept and effects of force majeure, it is also worth taking care of the information obligation.

 

Exampe: Let’s imagine a situation where two parties have entered into a contract for the construction, transportation, and installation of carpentry in a shopping mall, with a completion deadline of May 15th, 2020. On the planned delivery date, the Contractor informs the Ordering Party that due to a force majeure event, specifically the coronavirus epidemic, the contract could not be executed on time. Although the Ordering Party  had not been previously informed of any potential delay, the Contractor’s reliance on the coronavirus outbreak and associated restrictions would not be sufficient to justify the breach of contract. Such an unfortunate situation could have been avoided if the parties had displayed good faith by disclosing all relevant circumstances. If the Contractor had informed the Ordering Party  in advance, the latter could have taken appropriate measures to mitigate or alleviate the consequences of the delay.

The core of the information obligation should therefore lead to inform  the other party immediately about the occurrence of the event constituting a case of force majeure, the circumstances of this event, the estimated time of its occurrence and the proposed course of action. The parties should also contractually determine whether the occurrence of force majeure needs to be documented. While in case of a coronavirus epidemic it is unlikely that a foreign contractor would not be aware of its occurrence, in case of events related to the operation of public authority in a given country, an entrepreneur based in another country may not be aware of such difficulties at all. 

Force majeure in international contracts

Undoubtedly, the events of recent years have increased the awareness of entrepreneurs in terms of introducing contractual provisions regarding the occurrence of extraordinary situations, unforeseeable at the time of concluding the contract. As with many other contractual provisions, these are also intended to remove the parties’ uncertainty about how to proceed in a particular case.

Joanna Lubecka
attorney

[1] Judgment of the Court of Appeal in Lublin, November 19th, 2019, file ref: III APa 15/19.

02

Contact

Law Firm in Poznan

ul. Nowowiejskiego 53/2
61-734 Poznań
Fill in the form

    Information clause on processing of personal data.

    * required fields.

    lubecka.law 2024©
    Wdrożenie i rozwój: Fisze